Skip Navigation

Gaywoods Stormwater Pond

As a part of the County's effort in protecting our waters, the stormwater pond (Pond - 11023) within the Gaywoods community was selected for upgrades to help reduce stormwater pollution draining into our streams.

Various public events will be held throughout the project phases for residents to learn about the project and to provide input design of the project. Check out the Public events and project schedule table at the bottom of the page for more information.

 

PROJECT FACTS
Project Status: In Design
Total Drainage Area: 21.66 Ac
Total Percent Impervious: 20%
Total Stream Project Length: N/A
Estimated Cost: $200,000
Monitoring: No
Watershed: Anacostia River
Contact: Brett Long
Email: Brett.Long@montgomerycountymd.gov
Phone: (240) 499-8531

*Information is subject to change

Image of Gaywoods Project Map

To download, click (PDF, 1.46 MB).

 

Public Events and Project Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting Winter 2014/2015 TBD
Concept Design Plans Winter 2014/2015  
Community Walk Summer 2014 onsite
Final Plans Fall 2015  
Construction Winter 2015/2016  

*Project schedule is tentative and dates are subject to change.