PROJECT FACTS
Project Status: In Design
Total Drainage Area: 21.66 Ac
Total Percent Impervious: 20%
Total Stream Project Length: N/A
Estimated Cost: $200,000
Monitoring: No
Watershed: Anacostia River
Contact: Brett Long
Email: Brett.Long@montgomerycountymd.gov
Phone: (240) 499-8531

*Information is subject to change

Image of Gaywoods Project Map

To download, click (PDF, 1.46 MB).

 

Public Events and Project Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting On Hold TBD
Concept Design Plans On Hold  
Community Walk On Hold onsite
Final Plans On Hold  
Construction On Hold  