Greencastle Park and Ride Low Impact Development Retrofit

As a part of the county's effort in protecting our waters, the Greencastle Park & Ride Lot was selected for a low impact development (LID) retrofit project to help reduce stormwater pollution that drains into our streams. LID projects generally involve installing small-scale stormwater practices on county property to capture water from roadways, parking lots, and sidewalks during storms. 

Various public events will be held throughout the project phases for residents to learn about the project and to provide input on the design of the project. Check out the Project Schedule at the bottom of the page for more information.

 

                              

 

PROJECT FACTS
Project Status: In Design
Total Drainage Area: 3.3 Ac
Total Percent Impervious: 42%
Total Stream Project Length: N/A
Estimated Cost: $570,000
Monitoring: No
Watershed: Paint Branch
Contact: Brett Long
Email: Brett.Long@montgomerycountymd.gov
Phone: (240) 499-8531

     *Information is subject to change

    Image of Greencastle Park and Ride

    To download, click (PDF, 511 KB)

 

Public Events and Site Schedule
Event Date / Time Location
Survey and Site Analysis Winter 2013  
Preliminary Site Assessment Winter 2013  
Public Meeting Spring 2014 Greencastle Lake Community Building
Concept Design Plans Spring 2014  
Final Plans Winter 2014  
Construction Winter/Spring 2015  

*Project schedule is tentative and dates are subject to change.