Longmead Crossing Stormwater Pond

As a part of the County's effort in protecting our waters, the stormwater pond (Pond - 11060) within the Longmead Crossing community was selected for upgrade to help reduce stormwater pollution draining into our streams.

Various public events will be held throughout the project phases for residents to learn about the project and to provide input on the design of the project. Check out the public events and project schedule table at the bottom of the page for more information.

                               

 

PROJECT FACTS
Project Status: In Design
Total Drainage Area: 19.33 Ac
Total Percent Impervious: 41.33%
Total Stream Project Length: N/A
Estimated Cost: $550,000
Monitoring: No
Watershed: Anacostia River
Contact: Brett Long
Email: Brett.Long@montgomerycountymd.gov
Phone: (240) 499-8531

*Information is subject to change

Image of Longmead Crossing Map

To download, click (PDF, 546 KB)

 

Public Events and Project Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting February 2014 Longmead Crossing
Concept Design Plans Summer 2014  
Final Plans Spring 2015  
Construction Summer 2015  

*Project schedule is tentative and dates are subject to change.