Springbrook / Homestead Estates Green Streets

As a part of the County's effort in protecting our waters, the Springbrook / Homestead Estates neighborhoods were selected for a Green Streets project to help reduce stormwater pollution that drains into our streams. Green Streets projects generally involve installing small-scale stormwater practices within the County right-of-way to capture water from roadways and sidewalks during storms.

Various public events will be held throughout the project phases for residents to learn about the project and to provide input on the design of the project. Check out the Project Schedule at the bottom of the page for more information!

 

                             

 

PROJECT FACTS
Project Status: In Design
Total Drainage Area: 170 Ac
Total Percent Impervious: 24%
Total Stream Project Length: N/A
Estimated Cost: TBD
Monitoring: No
Watershed: Anacostia River
Contact: Phil Jones
Email: phil.jones@montgomerycountymd.gov
Phone: (240) 499-8531

     *Information is subject to change

      Image of Springbrook and Homestead Estates

     To download, click (PDF, 1.71 MB)

 

Public Events and Site Schedule
Event Date / Time Location
Preliminary Site Assessment Summer 2013  
Public Meeting February 26, 2014 / 6:30p.m. - 8:00p.m.

White Oak Library - Large Meeting Room / 11701 New Hampshire Ave. Silver Spring, MD 20904

Draft Designs Spring 2014  
Design Update Meeting and Community Walk Summer 2014  
Final Designs Fall 2014  
Construction Duration Throughout 2015  

*Project schedule is tentative and dates are subject to change.