Skip Navigation

Tuckerman Lane Regional Stormwater Pond

As a part of the county's effort to protect our waters, the stormwater pond within the Tuckerman community was selected for upgrade to help reduce stormwater pollution draining into our streams.

Various public events will be held through out the project phases for residents to learn about the project and to provide input on the design of the project. Check out the Project Schedule at the bottom of the page for more information!




Project Status: In Design
Total Drainage Area: 364.3 Ac
Total Percent Impervious: 34%
Total Stream Project Length: N/A
Estimated Cost: $94,000
Monitoring: No
Watershed: Rock Creek
Contact: Christy Ciarametaro
Phone: (240) 777-7720

     *Information is subject to change

    Image of Tuckerman Lane Stormwater Pond

    To download, click (PDF, 1.47 MB)


Public Events and Site Schedule
Event Date / Time Location
Survey and Site Analysis Completed Fall 2013  
Preliminary Site Assessment Completed Fall 2013  
Public Meeting Fall 2015 TBD
Concept Design Plans Completed Fall 2014  
Community Walk Winter 2015  
Final Plans Spring 2015  
Construction Spring 2016  

*Project schedule is tentative and dates are subject to change.