Skip Navigation
Department of General Services, Division of Building Design and Construction

Silver Spring Library

Back to: BDC HomeNeighborhood ProjectsSilver Spring Projects › Silver Spring Library

Show the project location in google mapWayne Ave. & Fenton St.
Silver Spring, MD 20910

Funding/Expenditure Schedule:
Current or Recommended

 

Project Team

Architect
The Lukmire Partnership
(703) 998-0101
Contractor
Costello Construction
(410) 740-9500

Montgomery County Government
Department of General Services

Division of Building Design and Construction
Ernest Lunsford, Chief
(240) 777-6097
Project Manager
Susanne Churchill
(240) 777-6113
Team Leader
Name
Phone #

Current Phase: Under Construction

Project Status and Status:

Construction Progress Bulletin - January 2014

  • Continued working on steel erection
  • Completed installation of steel trusses at line 1 and 3
  • Completed welding splice connections at cantilevered truss
  • Installed transfer girder at 3rd floor
  • Continued installing roof deck
  • Poured concrete at loading dock
  • Began installation of steel stud exterior framing at the west side through 5th floor
  • Completed CMU walls at 2nd floor east elevation
  • Started CMU walls at 5th floor
  • Completed below grade electrical work at Pavilion
  • Installed second temporary electrical poser
  • Installed branch circuitry at lower level
  • Installed electrical rough-in and panel boards at main electrical room
  • Continued spray fireproofing of steel at west side
  • Begin construction of sample wall panel

Live Construction Web Camera

Construction Progress Images:

Change to Slide Show view. Click an image to view in full size.

Silver Spring Library - construction image

View from 5th floor of the Wayne Ave Garage. CMU back-up is in progress at the second floor. 4th floor framing west of x-1 line is nearly complete.5th floor and roof framing west of x-1 line is in progress. Spray fireproofing is underway.

Silver Spring Library - construction image

View from southwest corner of site. Steel frame for the pavilion is nearing completion. Outriggers at 5th floor level visible. Pallets of cast stone in foreground.

Silver Spring Library - construction image

Trusses at 3-Line and 4-Line with framing at 5th Floor and Main Roof.

Silver Spring Library - construction image

Pavilion framing.

Silver Spring Library - construction image

Truss at Line-4, right side.

Silver Spring Library - construction image

Truss at Line-4, left side.

Silver Spring Library - construction image

Pavilion 5th Fl. metal deck installation.

Silver Spring Library - Construction image

View from 5th floor of the Wayne Ave Garage. CMU back-up is in progress at the second floor, as the formwork is being installed for the concrete wall north of elevator 2&3. Steel has been installed up the 4th floor in the main portion of the building, with areas of the 5th floor and roof installed near stair/elev #1. Trusses 3 and 4 are visible in the background.

Silver Spring Library - Construction image

Masonry walls being built in basement.

Silver Spring Library - Construction image

Steel erection in progress at pavilion.

Silver Spring Library - Construction image

Trusses 3 and 4 have been installed at the 5th floor. Pavilion has been framed up to the 5th floor. CMU back-up in progress at the 2nd floor.

Silver Spring Library - Construction image

Precast lintels installed in masonry openings.

 

This project will provide the Silver Spring community with a new library located within the CBD. The new library will be approximately 63,000 gross square feet in size and is intended to meet the unique requirements of an increasingly urban, ethnically and culturally diverse residential and business community. A site selection committee was formed in January of 2001 to recommend a potential site that meets an established set of criteria. The CIP includes planning and construction money for this project. Montgomery County has prepared an RFP to solicit interest from developers interested in constructing a residential project adjacent to the future library. The project will also include an art gallery. The project will be a LEED Silver building. The State has also expressed an interest in incorporating a Purple Line station into this project.

Public Meetings:

Four charettes were held between April and July 2009 to obtain community feedback on the exterior building and open space design for the Silver Spring Library Building. A fifth public meeting was held November 7, 2009 to present more defined exterior and public space designs to the community. The architect’s presentations and notes from each charrette and meeting can be found in the Library Design Charrettes section below. A meeting held in August 2010 solicited comments from the community about options to be investigated to bring the cost of the building within the budget. A final meeting was held in November 2010 to present the design resulting for the studied options.

Architecture

The design of the Silver Spring Library will be determined through a charrette process seeking to obtain input from as many interested participants as possible.

What is a Charrette?
The French word “charrette” means “cart” and is often used to describe concentrated work effort expended by art and architecture students to meet a project deadline. This use of the term is said to originate from the École des Beaux Arts in Paris during the 19th century, where proctors circulated a cart, or “charrette,” to collect drawings from the students.

The resulting design should be a significant, positive addition to the Silver Spring community.

Library Design Charrettes and Public Meetings:

February 21, 2012
REOI - Presubmission Conference
 
Nov. 3, 2011
Joint Meeting of Pedestrian and Traffic Safety Advisory Committee and Silver Spring Citizens Advisory Board Pedestrian and Transprotation Committee
 
July 11, 2011
Silver Spring Library–meeting with FOL and LAC
 
November 30, 2010
Silver Spring Library Final Design Update Presentation
 
August 26, 2010
Silver Spring Library Design Update Presentation
 
November 7, 2009
Silver Spring Library Schematic Design Presentation
 
July 9, 2009
Silver Spring Library Exterior and Landscape Design Charrette Meeting 4
 
June 18, 2009
Silver Spring Library Exterior and Landscape Design Charrette Meeting 3
 
May 7, 2009
Silver Spring Library Exterior and Landscape Design Charrette Meeting 2
 
April 16, 2009
Silver Spring Library Design Charrette Meeting 1 LEED Score Sheet
Silver Spring Library Exterior and Landscape Design Charrette Meeting 1
 
Additional Documents:
Updated Designs and Evaluation Criteria for Fourth Workshop
Design Options Presented for Third Meeting Design Charrette
Introduction for Third Meeting Design Charrette
Design Options Presented for Second Meeting Design Charrette
Introduction for Second Meeting Design Charrette

Studies:

Frequently Asked Questions:

  • What is the timeline for the project?

    Project documents were issued for bid in August 2012. The bid period is about 30 to 45 days. Bids were received from the pre-qualified contractors on November 7, 2012 and the lowest bids were within budget. The contract was awarded to Costello Construction, the lowest bidder. The County’s procedural issues (checking insurance and bond information) was completed prior to signing the contract and issuing the notice to proceed. The building construction started shortly thereafter, January 7, 2013.

    Construction is planned to last 22 months followed by up to 8 weeks for the Library to actually move in all the books and media collections

    The construction of the project was divided into two phases; the first was the utility relocation work, followed by the actual construction of the building. This allowed us to get a head start on the construction by completing the utility relocation while we continued to design and document the building.

    The utility relocation work is now complete; The County has relocated both the storm and sanitary sewers and has built conduit under the roadway for the “dry” utilities to relocate their cables from the telephone poles along Wayne Ave. The utility companies, Pepco, Verizon and Comcast, have finished relocating their cables.

    Fenton Street has been repaved and the parking meters have been reinstalled along Bonifant Street.

    The construction drawings were submitted to the Department of Permitting Services for review in April 2012 and we have a building permit.

    We conducted a pre-qualification review of general contractors interested in bidding on the project, through the County’s REOI process (Request for Expression of Interest). This was completed and 8 contractors were pre-qualified and were eligible to bid on the project


  • How much will the project cost in total? Where is this funding coming from?

    The County Council has approved $69,529,000 for the entire project which includes the purchase of the land, utility relocation and upgrades, actual building construction, furniture and equipment, security, telephone systems and computers, new books and media, and consultant fees, permit costs.

    The funding comes from G.O. Bonds, General Revenue, and Pay-go and State grants.


  • What are the dimensions of the building? How many square feet, floors, etc.?

    The building is five floors plus a basement. The footprint of the first floor is split by the right-of-way for the future Purple Line light rail resulting in a main building to the west of the ROW and the “Pavilion” to the right, along Fenton Street. These join up at the third floor.

    The floors vary in size, but the gross area of the overall building is about 90,000 square feet.

    There are two entrances into the building from Wayne Avenue, both of which provides access to elevators up to the Library and to the building generally. There is another entrance from Fenton Street directly to the third floor, which is the entry floor for the library.

    The Library occupies the third, fourth and fifth floors. The third floor is the entry floor to the library and access is provided from the Wayne Ave entrance and the Fenton Street Entrance.

    The third floor houses the meeting rooms, media collection, the Young Adult area, the Disability Resource Center and the main circulation work area.

    The 4th floor is the location for the adult collections with a large quiet study room overlooking part of Silver Spring.

    The 5th floor is the children’s floor with an integrated early learning area, program room, tutor rooms and another meeting room.

    There are computer workstations throughout the entire building as well as seating and electric outlets for those who choose to bring their own laptops or tablets.

    Pyramid Atlantic, the non-profit art group, occupies part of the basement, part of the first floor and the second floor.

    A coffee shop is planned for the first floor of the Pavilion.


  • What amenities will the building have? Any public meeting spaces or mixed use areas in the facility? If so, will the community be able to rent this space?

    The Library has a number of meeting spaces of different sizes. These include public meeting rooms, tutor rooms, group study rooms, a quiet study room, a Children’s program room, and computer labs. The meeting rooms will be available to the public for a fee via the County’s on-line reservations (CUPS). The other rooms are for Library planned events or can be signed up at the library when not in use otherwise.

    One of the guiding principals for the design of the building was flexibility. We wanted spaces to be able to be used in more than one way. The major meeting rooms on the third floor, which is the entry floor of the library, when not signed out for meetings can be used by the public as an area for casual computer use, with tables and outlets for them to bring their laptops and plug in.

    The computer labs will be used to provide training classes but will be available for general use when classes are not being run.

    The Children’s Program room, when not being used for a programmed event such as story-time, can be used by children and caregivers for other fun and educational learning.

    The Library will also have a Disability Resource Center and DPL is working to develop the specific program for the use of the space.

    Pyramid Atlantic will have an art gallery and a store located on the first level and offers classes to the public at the second floor studio space. They will also conduct workshops and classes for the Library on a regular basis.

    The route of the future Purple Line crosses the site and a stop will be located under the overhang of the building at grade level.

    A public open space is located next to the building fronting onto Bonifant Street which will have both paved areas and green space.

    Green roofs are used at the top of the main building and the roof of the Pavilion. These are primarily for storm water management; the roof of the main building will be sedums and other low maintenance plants, but the roof of the Pavilion will be visible from the children’s floor and will be designed to be seen.


  • How many people will be employed by the library?

    We anticipate 27 full time staff and 14 part time staff for shelving to be distributed over the time the Library will be open.

Links of Interest:

Montgomery County Public Libraries
Montgomery County Public Libraries Silver Spring Library Project Page

Change to Slide Show view. Click an image to view in full size.

Vicinity Map

Silver Spring Library - Vicinity Map

Click the image to view the location in Google Map.

Site Map

Silver Spring Library - Site Map

Click the image to view in full size.

Basement Floor Plan

Silver Spring Library - Basement Floor Plan

First Floor Plan

Silver Spring Library - First Floor Plan

Second Floor Plan

Silver Spring Library - Second Floor Plan

Third Floor Plan

Silver Spring Library - Third Floor Plan

Fourth Floor Plan

Silver Spring Library - Fourth Floor Plan

Fifth Floor Plan

Silver Spring Library - Fifth Floor Plan

View from Wayne Avenue

Silver Spring Library - View from Wayne Avenue

4th & 5th Floor Design Concept

Silver Spring Library - 4th & 5th Floor Design Concept

4th & 5th Floor Design Concept

Silver Spring Library - 4th & 5th Floor Design Concept

4th & 5th Floor Design Concept

Silver Spring Library - 4th & 5th Floor Design Concept

View Inside Fourth Floor Towards Group Study

Silver Spring Library - View Inside Fourth Floor Towards Group Study

View Inside Third Floor Stairs and Young Adults

Silver Spring Library - View Inside Third Floor Stairs and Young Adults

View Inside Fourth Floor from Elevators

Silver Spring Library - View Inside Fourth Floor from Elevators

View Inside Fourth Floor from Group Study

Silver Spring Library - View Inside Fourth Floor from Group Study

View Inside Fourth Floor to Group Study

Silver Spring Library - View Inside Fourth Floor to Group Study

Landscape Concept

Silver Spring Library - Landscape Concept