Skip Navigation
Department of General Services, Division of Building Design and Construction

Multi-Agency Service Park (MASP) & Public Safety Training Academy (PSTA) - Project 1: Site Development

Back to: OSP HomeNeighborhood ProjectsUp-County ProjectsMASP & PSTA › Project 1: Site Development

Show the project location in google map8701 Snouffer School Road
Gaithersburg, MD 20879

MASP & PSTA - Overall Site Plan

Funding/Expenditure Schedule

 

Project Team

Architect
Baker and Associates
3601 Eisenhower Ave. 6th Floor
Alexandria, VA 22304
Contractor
Pleasants Construction, Inc.
24024 Frederick Road
Clarksburg, MD 20871
 

Montgomery County Government
Department of General Services

Office of Special Projects
Hamid Omidvar, AIA, Chief
240-777-6126
Project Manager
Ali Davoodi, RA,
240-777-6009
Team Leader
Name
Phone #
 

The Montgomery County Multi Agency Service Park (MASP) & Public Safety Training Academy (PSTA) includes 4 projects:

This project is Completed.

Project Status and Schedule:

Design Start: 9/1/2012
Construction Start: 7/1/2013
Construction Completed: 11/15/2014

 

The Shady Grove Sector Plan, approved by the County Council in 2005, calls for transitioning the area around the Shady Grove Metro from light industrial uses to transit-oriented development. To accomplish this goal, the County Service Park facilities, which are located in the heart of the planning area along Crabbs Branch Way, must be relocated.

This project provides graded pads for Project 2, 3, and 4. The rough grading of the site, installation of site utilities to serve the future projects within the site, installation of storm water management infrastructure, development of the Turkey Thicket Drive and associated paving and landscaping.

Phase 1 Construction:
Rough Grading including building pads for Project 2; MCPS Food Distribution Relocation and Garage is completed.
 
Phase 2, 3 & 4 Construction:
Rough Grading including building pads for Project 3; Public Safety Training Academy and Project 4 MCPS and M-NCPPC Maintenance on east side are completed.
The work associated with the construction of Turkey Thicket Drive is completed.

Links of Interest:

Smart Growth Initiative

Click an image to view in full size.

Overall Site Plan

MASP & PSTA - Overall Site Plan

Click the image to view in full size.

Vicinity Map

MASP & PSTA - Vicinity Map

Click the image to view the location in Google Map.

MASP & PSTA - Construction image
MASP & PSTA - Construction image
MASP & PSTA - Construction image
MASP & PSTA - Construction image
MASP & PSTA - Construction image
MASP & PSTA - Construction image