2009 CONSTRUCTION SEASON:
| Street Name |
From: |
To: |
Start Date |
Status |
| Denfield Rd |
Wexford Dr |
Connecticut Ave |
5/18/2009 |
Complete |
| Decatur Ave |
Wexford Dr |
Connecticut Ave |
5/18/2009 |
Complete |
| Lawrence Ave |
Decatur Ave |
Connecticut Ave |
5/18/2010 |
Complete |
| Crystal Rock DR |
Germantown Rd |
E.O.M. |
6/1/2009 |
Complete |
| Calverton Blvd |
Cherry Hill Rd |
Galway Dr (PG County Line) |
6/1/2009 |
Complete |
| Father Hurley Blvd |
Wisteria Dr |
Crystal Rock Dr |
6/1/2009 |
Complete |
| Wisteria Dr |
Germantown Rd |
Father Hurley Blvd |
6/1/2009 |
Complete |
| Wisteria Dr Ph 2 |
Father Hurley Blvd |
Sea Breeze Ct. |
9/8/2009 |
60% Complete |
| Bel Pre Rd |
Georgia Ave |
Layhill Rd |
6/29/2009 |
Complete |
| Amherst Ave |
Windham Lane |
Arcola Ave |
7/20/2009 |
Complete |
| Nicholson La |
Rockville Pike |
Old Georgetown Rd |
7/3/2009 |
Complete |
| Huntington Pkwy |
Bradley Blvd |
Old Georgetown Rd |
8/17/2009 |
Complete |
| Seven Locks Rd |
Democracy Blvd |
Bradley Blvd |
May 2010 |
Scheduled |
| Gainsbourgh Rd |
Tuckerman La |
Democracy Blvd |
9/7/2009 |
Scheduled |
| Travilah Rd |
RT.28 |
Dufief Mill Rd |
TBD |
Scheduled |
| Grosvenor La |
Cheshire Dr |
Rockville Pike |
Sept 2009 |
Complete |
| Fenton St |
Wayne Ave |
Philadelphia Ave |
TBD |
Scheduled |
|
|
|
|
|
|
| |
Proposed Night Work |
|
|
|
|
|
|
|
|
|
| This schedule may be changed and substitutions may be made at any time due to weather or operational reasons. |
|