The Primary/Arterial Roads Resurfacing Programs are instituted to protect and maintain the County’s primary roadway transportation infrastructure. The County has approximately 957 lane miles of Primary/Arterial roads. The scope of work includes milling, repair, bituminous concrete resurfacing, patching and revitalization. Roadway resurfacing is the process of applying a new wearing surface on County-maintained roadways throughout the County. This Program provides for systematic, full-service and coordinated revitalization to enhance access and safety for all users.
2012 CONSTRUCTION SEASON: Update: 5/9/2012
Click on the road name (if underlined) to read or download a Project Newsletter describing the scope of the project.
Check back periodically as projects get added or scheduled. This schedule may be changed and substitutions may be made at any time due to weather or operational reasons.
| Road Name |
From: |
To: |
Project Scope |
Start Date |
Status |
| Appleridge Road |
Montgomery Village Ave. |
Watkins Mill Rd. |
HMA |
TBD |
|
| Bells Mill Road |
Seven Locks Rd. |
Falls Rd. |
2x Micro |
3/26/2012 |
70% Complete |
| Bushey Drive |
Veirs Mill Rd. |
Littleton St. |
Patching |
Summer/Fall '12 |
|
| Crabbs Branch Way |
Shady Grove Rd. |
Redland Rd. |
Patching |
Summer/Fall '12 |
|
| Dawson Farm Road |
Germantown Rd. |
Father Hurley Blvd. |
2x Micro |
4/26/2012 |
Scheduled |
| Edson Lane |
MD 187 |
MD 355 |
2x Micro |
3/19/2012 |
70% Complete |
| Emory Lane |
Muncaster Mill Rd. |
Georgia Ave. |
HMA |
3/19/2012 |
100% Complete |
| Ennalls Avenue |
Veirs Mill Rd. |
Georgia Ave. |
HMA |
4/10/2012 |
100% Complete |
| Executive Boulevard |
Jefferson St. |
Old Georgetown Rd. |
HMA |
5/29/2012 |
Scheduled |
| Fenton Street |
Wayne Ave. |
Philadelphia Ave. |
HMA |
6/4/2012 |
Scheduled |
| Fenton Street |
Wayne Ave. |
Cameron St. |
HMA |
Summer 2012 |
|
| Ferrara Drive |
Veirs Mill Rd. |
Mahan Rd. |
2x Micro |
4/12/2012 |
Scheduled |
| Fields Road |
I-270 Ramp |
Sam Eig Hwy. |
2x Micro |
7/9/2012 |
Scheduled |
| Garrett Park Road |
Dewey Rd. |
Schuykill Rd. |
Patching |
Summer/Fall '12 |
|
| Heathfield Road |
Georgia Ave. |
Parkland Dr. |
2x Micro |
8/9/2012 |
Scheduled |
| Hewitt Avenue |
Georgia Ave. |
Rippling Brook Dr. |
Patching |
Summer/Fall '12 |
|
| Hipsley Mill Road |
Damascus Rd. |
End of Maintenance |
Patching |
Summer/Fall '12 |
|
| Howard Chapel Drive |
Damascus Rd. |
Gue Rd. |
Patching |
Summer/Fall '12 |
|
| Jones Lane |
MD 28 |
Turkey Foot Rd. |
HMA |
Fall 2012 |
|
| Lyttonsville Place |
Lyttonsville Road |
Brookville Road |
HMA |
Summer 2012 |
|
| Mahan Road |
Ferrara Dr. |
Dewey Rd. |
2x Micro |
4/18/2012 |
Scheduled |
| Mariana Drive |
Parkland Dr. |
Bauer Dr. |
2x Micro |
8/7/2012 |
Scheduled |
| Mateny Road |
Clopper Rd. |
Wheatridge Dr. |
HMA |
Fall 2012 |
|
| Medical Center Drive |
Great Seneca Hwy. |
Key West Ave. |
HMA |
5/30/2012 |
Scheduled |
| Medical Center Way |
Shady Grove Rd. |
Medical Center Way |
HMA |
Fall 2012 |
|
| Middlebrook Road |
MD 355 |
Great Seneca Hwy. |
2x Micro |
8/15/2011 |
70% Complete |
| Mink Hollow Road |
MD 108 |
End of Maintenance |
HMA |
Fall 2012 |
|
| Newport Mill Road |
Veirs Mill Rd. |
University Blvd. |
Patching |
Summer/Fall '12 |
|
| Old Stage Road |
Tilden La. |
Hitching Post La. |
Patching |
Summer/Fall '12 |
|
| Omega Drive |
Key West Ave. |
I-270 Ramp |
2x Micro |
7/1/2012 |
Scheduled |
| Parkland Drive |
Chesterfield Rd. |
Aspen Hill Rd. |
2x Micro |
7/23/2012 |
Scheduled |
| Plyers Mill Road |
Georgia Ave. |
End of Maintenance |
Patching |
Summer/Fall '12 |
|
| Randolph Road |
Veirs Mill Rd. |
Connecticut Ave. |
HMA |
Fall 2012 |
|
| Ridge Drive |
Glen Mill Rd. |
Watts Branch Dr. |
Patching |
Summer/Fall '12 |
|
| Seven Locks Road |
MacArthur Blvd. |
River Road |
HMA |
5/7/2012 |
5% Complete |
| Stewart Lane |
Old Columbia Pike |
Lockwood Dr. |
2x Micro |
4/9/2012 |
70% Complete |
| Stoney Creek Road |
Travilah Rd. |
River Rd. |
HMA |
TBD |
|
| Tenbrook Drive |
Forest Glen Rd. |
Dennis Ave. |
HMA |
Summer 2012 |
|
| Tildenwood Drive |
Montrose Rd. |
Old Stage Rd. |
Patching |
Summer/Fall '12 |
|
| Travilah Road |
River Road |
Dufief Mill Road |
ARRA |
Spring 2012 |
95% Complete |
| Waring Station Road |
Wisteria Drive |
Middlebrook Road |
HMA |
4/9/2012 |
70% Complete |
| Westlake Drive |
Democracy Blvd. |
Tuckerman La. |
HMA |
TBD |
|
| Wightman Road |
Brink Road |
Goshen Road |
ARRA |
Spring 2012 |
10% Complete |
Click on the underlined link(s) provided below to view respective project schedules:
TBD = Schedule for this project To Be Determined at a later date.
|