|
||
Paul S. Sarbanes Silver Spring Transit Center Project Team Montgomery County Government Department of General Services Manager III Frank Roberts (240) 777-6084 Project Managers Robert Stout (240) 777-6159 Tim O'Gwin (240) 777-6051 Architect Zimmer Gunsul Frasca Architects Fritz Schellkopf (202) 380-3058 Project Engineer Parsons Brinckerhoff Gerald S. Jannetti (410) 385-4193 General Contractor Foulger-Pratt Contracting John P. Barron, President (240) 499-9694 |
||
Project Description The
proposed
It
will feature;
The new facility will replace and significantly increase the capacity, safety and efficiency of a more than thirty year old, aging, surface transit facility in the heart of the newly revitalized downtown Silver Spring, eliminate the existing traffic conflicts, increase pedestrian safety, facilitate multi-modal transfers and provide well-developed bicycle access into the mass transit site. Planning for this facility has carefully addressed and considered future extensions of mass transit such as the Bi-County Transitway and the District of Columbia/Georgia Avenue Corridor facility as well as the planned regional Metropolitan Branch and Capital Crescent Trails and the Silver Spring Green Trail. The new The project is being funded through from the Federal Transit Administration (53%), Maryland Mass Transit Administration (11%) and Montgomery County (36%). The Interim Operations Site for bus
traffic and passenger waiting areas continues to function
successfully, as it has since the start of operations in September
2008. To allow for construction activities at the southeast side of
the project site, access to the MARC outbound tracks has been relocated to the west side of the tracks via
East-West Highway and the south side of Ramsey Avenue has been
closed to allow construction of entrances to the Transit Center. The facility is approximately 95% complete. Ongoing
activities at this time are elevator and escalator installation,
installation of large glass panels on top of
the canopies, installation of electrical and mechanical equipment,
lights, signs, landscaping, tree planters and work in the TRiPS Store, Intercity Bus
and general office areas. Work continues on the three entrances to
the transit center from Colesville Road, Ramsey Avenue and Bonifant
Street. The concrete bus road at the 305 level (ground floor) is 85%
complete. Small retaining walls and landscaping curbs have been constructed along the Metropolitan Branch Trail
and the trail is being paved. The adjacent contractor has paved the future extension of Ripley Street. A new
sidewalk and street lights along Colesville Road has been
constructed. Granite pavers are being installed in the Metro Plaza.. The County has determined that the
concrete slab thickness for the middle and top level elevated slabs
fall outside the allowable construction tolerances for thickness.
Approximately 37% (as determined through examination of the drive
aisle areas on the 330 and 350 level decks) of the elevated deck
area is in compliance, while 42% exceeds the allowable thickness and
21% is less than the allowable thickness. Analyses to determine the impacts of
the non-compliant work are ongoing. In addition, in some areas of insufficient thickness, the concrete coverage of the reinforcing bars and post tension cables is less than the allowable. A letter outlining the deficiency has been issued by the
County's Contract Administrator. The General Contractor submitted a plan for corrective action
on March 15, 2012 but it omitted structural data. A resubmission was
submitted on April 6th and a technical briefing was held on April
11th. The issues are being reviewed. The final completion date is indeterminate at this time. Funding Please visit here for information regarding Transit services during construction of the Paul S. Sarbanes Transit Center. |
||
| Current
Construction Images (click on image to view full size) Project Images |
||
|
Links
of Interest
Montgomery County Department of Transportation Celebrate Silver Spring Foundation - Paul S. Sarbanes Transit Center |
||
Division of Building Design and Construction - Department of General Services
11th Floor, 101 Monroe Street, Rockville MD 20850













































