Text Version      
Montgomery County Maryland top half of the county seal
Home | Translate   bottom half of the county seal
empty space above portal links
ResidentsGovernmentBusinessCulture


Return to: Bethesda-Chevy Chase Projects


Judicial Center Annex 

50 Maryland Ave
Rockville, Maryland 20850

Project Team:

Architect
AECOM Design
3101 Wilson, BLVD, Suite 900
Arlington, VA 22201

Montgomery County Government
Department of General Services
Office of Special Projects


Hamid Omidvar, AIA, Chief
240-777-6126


Project Manager
Randall Hawkins 
240-777-6099


Judicial Center Annex



 Important Notices

Between the dates from May 21, 2012 through August 13, 2012, a small portion of the overall construction work will take place in the evenings to early mornings between the hours of 8:00 pm through 7:00 am. This work must be completed during these times to avoid disrupting the Circuit Court. Regrettably, vibrations from the construction activity reverberate through the entire Judicial Center interfering with our electronic, digital court recording system which can make the recording of the court process unintelligible. Consequently, a transcript of the legal proceedings cannot be provided to the litigants or appellate courts which could cause devastating, unintended consequences for litigants. Additionally, the Circuit Court handles court and jury trials which can include criminal cases with sentences involving of life or death, family matters involving divorce, custody and termination of parental rights, which are highly emotional and can be catastrophic to the family element, and civil cases where judges and juries will determine the fate of businesses, medical malpractice suits, foreclosures, etc. All of these matters mentioned and many others not referenced are determined daily in the Judicial Center.


Every effort will be made to minimize noise. The work will include the following:

  1. Demolition of Concrete and Reconstruction at Helix Area (Noise generating activities includes Scaffolding, Concrete Trucks, Formwork, Jack Hammers, Hammer Drills, Concrete Vibrator, Debris placed in Dumpster). This activity will approximately start on May 21st and conclude on June 4th. The work is anticipated to be approximately 7 days during this period. The typical work shift is from 8:00 PM to 4:00 AM. All jack hammering will occur before 11:00 PM or during the day on Saturdays.

  2. Installation of Precast on New Annex (Noise generating activities will include Crane, Welding and Material Hoist, Back-Up Alarms). This activity will approximately start on July 9th and conclude on August 13th. The typical work shift is Monday – Friday from 8:00 PM to 4:00 AM.

  3. Demolition and Construction of New Generator Exhaust (Noise generating activities include Jack Hammers, Hammer Drills, Concrete Vibrator, Debris placed in Dumpster. This activity will approximately start on June 29th and conclude on July 9th. The work is anticipated to be approximately 3 days during this period. The typical work shift is from 8:00 PM to 4:00 AM. All jack hammering will occur before 11:00 PM or during the day on Saturdays.

We apologize for any inconvenience this may cause.


If you have questions or concerns during the evening operations, please contact Samuel Gillespie, Superintendent for Tompkins Builders, Inc., at (202) 438-0801 or Ray Steinmetz, Montgomery County Construction Representative, at (240) 672-5389. For questions or concerns during the day please contact Randall Hawkins, Montgomery County Representative at (240) 777-6099 or Bill Bishop, Tompkins representative at (301) 605-7915. For information regarding the Montgomery County Noise Ordinance program, please visit the following webpage: http://www.montgomerycountymd.gov/dectmpl.asp?url=/Content/dep/community/ordinance.asp.


 

Project Status: Construction Phase/strong>


 
Construction Progress Bulletin

  • Concrete work on the parking level and foundation walls has been completed. Concrete work on the terrace level that will connect to the lobby and sheriff’s department in the Judicial Annex will be finished in early May. The terrace level slab and all slabs above it will be post-tensioned concrete. Steel cables embedded in the concrete and are pulled after the concrete is poured to achieve thinner and stronger floor slabs.
  • Floors under construction are framed with a Sky Deck scaffolding system comprised of reusable and adjustable telescoping columns holding up a network of aluminum panels onto which the concrete floor is poured. This system allows the construction to progress faster with less waste.
  • The last of the variable air volume boxes is being replaced on the 3rd floor of the Judicial Center. All of the boxes in the VAV system have been replaced and balanced as part of a renovation to the cooling and heating system for the Judicial center.







Construction Progress Images

Judicial Center Annex

April 2012:

Crews worked on building the terrace level of the annex. This floor will connect to the existing Judicial Center through the lobby. Crews spent half of April laying out the rebar, electrical conduit, and steel tension cables all along the new floor before the concrete pour. The cables (blue) are held in place with tripod-like chairs before the concrete pour.

 

Judicial Center Annex

April 2012:

The cables (blue) are part of a post-tensioning system. The concrete is poured in sections on top of the rebar and cables. After a section is poured, each cable coming out of the side of slab is pulled to about 5,000 psi, transferring additional compressive strength to the concrete, allowing the slab to be thinner, and achieving higher ceilings heights in the new building.


Project Description

This project involves an addition to and renovation of the existing Judicial Center. The Judicial Center Annex is a six story building with one level underground parking and one level mechanical penthouse. The Annex provides ten additional courtrooms and administrative spaces. The renovation of the existing judicial center includes upgrading interior spaces, mechanical, electrical and plumbing upgrades. The project will be designed to comply with Leadership in Energy and Environmental Design (LEED) guidelines for LEED Silver (potentially Gold certification) which includes a green roof and roof mounted photovoltaic panels. The existing plaza and green spaces will be redesigned to invite public use of the space. The green space will include a water fountain, new trees, benches and a Memorial Walkway to receive the memorial plaques that will be relocated to allow for the construction of the Annex. Refer to the site plan image for the location of the Memorial Walkway.

The project consists of three phases. Phase one includes the existing Judicial Center HVAC renovation for floor 6-9 and the penthouse roof . Phase two includes the construction of the Annex and the phase three encompasses the interior renovation and upgrades of the remaining area of the existing Judicial Center.

PProject Animation


  

Funding/span>



 


Memorial Walkway

Memorial Walkway

(click to view image in full size)
Memorial Walkway

(click to view image in full size)



 
Project Images

Google Map
(cilck on image for map)
Site Plan
(click to view image full size)
Vicinity Map Site Plan
East View Rendering
(click to view image in full size)
West View Rendering
(click to view image full size)
East View Rendering West View Rendering
East Elevation
(click to view image in full size)
West Elevation
(click to view image in full size)
East Elevation West Elevation
North Elevation
(click to view image in full size)
South Elevation
(click to view image in full size)
North Elevation South Elevation
Level 1 Floor Plan
(click to view image in full size)
Level 2 Floor Plan
(click to view image in full size)
Level 1 Floor Plan Level 2 Floor Plan
Level 3 Floor Plan
(click to view image in full size)
Level 4 Floor Plan
(click to view image in full size)
Level 3 Floor Plan Level 4 Floor Plan
Level 5 Floor Plan
(click to view image in full size)
Terrace Level Floor Plan
(click to view image in full size)
Level 5 Floor Plan Terrace Level Floor Plan
Garage Floor Plan
(click to view image in full size)
Penthouse Floor Plan
(click to view image in full size)
Garage Floor Plan Penthouse Floor Plan
Roof Plan
(click to view image in full size)
Typical Court Room
(click to view image in full size)
Roof Plan Typical Court Room
Corridor Rendering
(click to view image in full size)
Court Room Rendering
(click to view image in full size)
Corridor Rendering Court Room Rendering

 

Links of Interest

Montgomery County Circuit Court

Government Center Complex, Rockville





Office of Special Projects - Department of General Services
9th Floor, 101 Monroe Street, Rockville MD 20850



Last edited: 5/21/2012