Hunters Woods III Stormwater Pond

 
In order to provide maintenance and to protect our streams the County selected the stormwater pond (Pond - 10797)  within the Hunters Woods III community for upgrade. The retrofit project will convert an existing dry pond (temporarily holds water after it rains) to a wet pond (permanently holds at least some water).  

The retrofit project will bring the pond up to current design standards, help reduce stormwater pollution draining into our streams, include additional safety features, and will enhance local ecology.

A public meeting was held during the concept stage of this project for residents to learn about the project and to provide input on the design of the project. 

 

Hunters Woods III Stormwater Pond Map
Download (PDF, 203KB)

 

Public Events and Site Schedule

Calendar Graphic

Preliminary Assessment

Summer 2011

Calendar Graphic

Survey and Site Analysis

Fall 2011

Calendar Graphic

Concept Design Plans

Summer 2012

Calendar Graphic

Public Meeting

September 20, 2012
Whetstone Community Center

Calendar Graphic

Permit Plans

Spring 2014

Calendar Graphic

Final Plans

Winter 2016

Calendar Graphic

Construction

Fall 2017

*Project schedule is tentative and dates are subject to change.

 