Whetstone Run Stormwater Ponds Management Project (Phase II)

 

As a part of the County's effort to protect our waters, five  stormwater ponds within the Whetstone Run Watershed were selected for restoration to help reduce stormwater pollution draining into our streams.  Two of the five stormwaterponds are included in phase II of the project. The other three stormwater ponds are part of phase 1 and have been constructed. 

Various public events were held throughout the project phases for residents to learn about the project and to provide input on the design of the project. Public events and project schedules may vary by site.

 

 

 

Whetstone Phase II Stormwater Ponds
To download, click (PDF, 2.01MB)

 

Sites:

Horizon Run Pond (11556)
  • Site Status: Construction Pending

  • Total Drainage Area: 55.7 acres

  • Impervious Area: 24 acres

  • Percent Impervious: 43%

Hamptons Pond (11370)
  • Site Status: Construction Pending

  • Total Drainage Area: 10.4 acres

  • Impervious Area: 5.5 acres

  • Percent Impervious: 53%

 

Hamptons Pond -11370

Located along Royal Bonnet Circle within the Hamptons Community.

Hamptons Pond

 

Public Events and Site Schedule

Calendar Graphic

Preliminary Site Assessment

October 2011

Calendar Graphic

Public Meeting

November 29, 2011
Upper County Community Center

Calendar Graphic

Concept Design Plans

March 2012

Calendar Graphic

HOA Update

October 27, 2014

Calendar Graphic

Final Plans

February 2016

Calendar Graphic

Construction

Start - November 2016  Finish - August 2017    

*Project schedule is tentative and dates are subject to change.

 