As a part of the County's effort to protect our waters, the stormwater pond (Pond - 11130) within the Kemp Mill community, was selected for upgrade to help reduce stormwater pollution draining into our streams.

Various public events will be held through out the project phases for residents to learn about the project and to provide input on the design of the project. Check out the Project Schedule and Documents table at the bottom of the page for more information!



Project Status: In Design
Total Drainage Area: 31.19 Ac
Total Percent Impervious: 26%
Total Stream Project Length: N/A
Estimated Cost: $429,936.54
Monitoring: No
Watershed: Anacostia River
Contact: Ryan Gardiner
Phone: (240) 499-8531

       *Information is subject to change.

       Image of Kemp Mill Stormwater Pond

     To download, click (PDF, 1.60 MB).


Public Events and Project Schedule
Event Date / Time Location
Survey and Site Analysis Spring 2013  
Preliminary Site Assessment Summer 2013  
Public Meeting July 21, 2015 Kemp Mill ES 411 Siisson St, Silver Spring
Concept Design Plans Spring 2014  
Community Walk TBD TBD
Final Plans Winter 2015  
Construction Summer 2016  

*Project schedule is tentative and dates are subject to change.

                                                             Project Documents

Public Meeting Flyer Kemp Mill Public Meeting Flyer (PDF 197KB)