AGENDA ITEM #SJ
January 28,2014
Introduction
MEMORANDUM
TO:
FROM:
County Council
Amanda Mihill, Legislative
Attorney~
~Michael
Faden, Senior Legislative Attorney
Introduction: Bill 11-14, Buildings
- Expedited Review
Electric Vehicle Charging Station Permits
SUBJECT:
Bill 11-14, Buildings - Electric Vehicle Charging Station Permits Expedited Review,
sponsored by Councilmembers Berliner, Floreen, and Riemer, Council Vice President Leventhal,
and Councilmembers EIrich, Andrews, and Navarro, is scheduled to be introduced on January 28,
2014. A public hearing is tentatively scheduled for February 11,2014 at 7:30 p.m.
Bill 11-14 would require the Department of Permitting Services to implement an expedited
review process for permits to install electric vehicle (EV) charging stations and require the
Department to charge reduced fees for those permits. Electric vehicle charging stations
will
be
more common and necessary as EV usage increases.
Councilmember Berliner explained the purpose of this Bill in his January 14
memorandum describing his proposed energy/environmental package. See ©20 of Bill 2-14,
Agenda Item SA.
This packet contains:
Billll-14
Legislative Request Report
F:\LAW\B [LLS\1411 Electric Vehicle Charging Station Permits\Intro Memo. Doc
Circle
#
1
3
 PDF to HTML - Convert PDF files to HTML files
Bill No.
11-14
Conceming: Buildings - Electric Vehicle
Charging Station Permits - Expedited
Review
Revised:
11/7/2013
Draft No. 1
Introduced:
January 28,2014
Expires:
July 28, 2015
Enacted: _ _ _ _ _ _ _ _ __
Executive: _ _ _ _ _ _ _ __
Effective: _ _ _ _ _ _ _ _ __
Sunset Date:
---!..!.No~n.!.::e:..._.
_ _ _ _ __
Ch. _ _, Laws of Mont. Co. _ __
COUNTY COUNCIL
FOR MONTGOMERY COUNTY, MARYLAND
By: Councilmembers Berliner, Floreen, and Riemer, Council Vice President Leventhal, and
Councilmembers EIrich, Andrews, and Navarro
AN
ACT to:
(1)
(2)
(2)
require the Department of Permitting Services to implement an expedited review
process for permits to install electric vehicle charging stations;
require the Department to charge reduced fees for permits to install electric vehicle
charging stations; and
generally amend County law regarding building permits.
By adding
Montgomery County Code
Chapter 8, Buildings
Section 8-24C
Boldface
Underlining
[Single boldface brackets]
Double underlining
[[Double boldface brackets]]
* * *
Heading or defined term.
Added to existing law by original bill,
Deletedfrom existing law by original bill,
Added by amendment.
Deletedfrom existing law or the bill by amendment.
Existing law unqffected by bill
The County Council for Montgomery County, Maryland approves the following Act:
 PDF to HTML - Convert PDF files to HTML files
Bill No. 11-14
1
Sec. 1. Section 8-24C is added as follows:
8-24C. Expedited review process for
ill!.
electric vehicle charging station.
2
3
The Department must adopt an expedited review process for each permit to
install an electric vehicle charging station. The application fee for each permit to
install an electric vehicle charging station must not exceed half the amount the
Department charges for
f!
similar permit.
Approved:
4
5
6
7
8
9
10
11
Craig
L.
Rice, President, County Council
Date
Approved:
12
13
14
Isiah Leggett, County Executive
Date
15
16
This is a correct copy ofCouncil action.
17
18
Linda M. Lauer, Clerk ofthe Council
Date
~
W\BILLS\1411 Electric Vehicle Charging Station Permits\BiII I.Doc
 PDF to HTML - Convert PDF files to HTML files
LEGISLATIVE REQUEST REPORT
Bill 11-14
Buildings
-
Electric Vehicle Charging Station Permits
DESCRIPTION:
Expedite Review
Would require the Department of Permitting Services to implement an
expedited review process for permits to install electric vehicle (EV)
charging stations, and to charge reduced fees for those permits.
EV charging stations will be more common and necessary as EV
usage increases, but obtaining a building permit can be subject to a
long and costly permitting process.
To create an expedited and less costly permitting process for EV
charging stations.
Department of Permitting Services
To be requested.
To be requested.
To be requested.
To be researched.
Amanda Mihill, 240-777-7815
To be researched.
PROBLEM:
GOALS AND
OBJECTIVES:
COORDINATION:
FISCAL IMPACT:
ECONOMIC
IMPACT:
EVALUATION:
EXPERIENCE
ELSEWHERE:
SOURCE OF
INFORMATION:
APPLICATION
WITHIN
MUNICIPALITIES:
PENALTIES:
Not applicable.