Special Capital Improvements Project Legislation
Wheaton Redevelopment Program (p150401)
In accordance with Section 302 of the County Charter and Section 20-1 ofthe
Montgomery County Code, I am forwarding the attached Special Capital Improvements Project
Legislation Authorization and. Legislative Request Report for Wheaton Redevelopment Program
(p150401).
This request is necessary because the local cost ofthe above projects now exceeds
the FY15 Special Capital Improvements Project Legislation threshold of $13,621,000 as set by
Executive Order. The purpose ofthe project is set forth below.
The Wheaton Redevelopment Program provides for the planning, studies, design,
and construction of an office building, public parking garage, and a town square on the site of
Parking Lot 13 and the Mid-County Regional Services Center (RSC)
in
Wheaton.
I recommend prompt passage ofthis legislation so as
to
advance this project.
IL:hpv
Attachments (4)
c:
Ana
Lopez van Balen, Director, Mid-County, Regional Services Center
AI Roshdieh, Department of Transportation
Mike Riley, M-MNCPPC
Bonnie Kirkland, Assistant Chief Administrative Officer
Jennifer A. Hughes, Director, Office of Management and Budget
 PDF to HTML - Convert PDF files to HTML files
Expedited Bill No. _ _ _ _ __
Concerning; Wheaton
Redevelopment Program
Revised:
Draft No.
furroduced: _ _ _ _ _ _ _ __
Enacted: _ _ _ _ _ _ _ _ __
Executive: _ _ _ _ _ _ _ __
Effective: _____________
S~clDare: ~N~on~e~
_________
Ch. --' Laws of Mont. Co. 2014
COUNTY COUNCIL
FOR MONTGOMERY COUNTY, MARYLAND
By: Council President at the Request ofthe County Executive
AN ACT
to authorize the planning, design, and consrruction of the office building, public parking
garage, and a town square on the site of Parking Lot 13 and the Mid·County Regional Services
Cenrer (RSC) in the Kensington·Wheaton Policy Area, Project No. 150401.
By adding to the laws of Montgomery County 2014
Boldface
Underliniria
[Single boldface brackets]
IDouble underlinina
.
[[Double boldface brackets]]
* * *
Heading or defined term.
Added to existing law by original bill.
Deletedfrom existing law by original bill.
Added by amendment.
Deletedfrom existing law or the bill by amendment.
Existing law unaffected by bill.
The County Council for Montgomery County, Maryland approves the following Act:
 PDF to HTML - Convert PDF files to HTML files
Section 1. The laws ofMontgomery County, Maryland, are amended
to
read as follows:
Montgomery County, Maryland, is authorized to plan, design. and construct the office
building, public parking garage, and a town square on the site ofParking Lot 13 and the Mid­
County Regional Services Center WC) in the Kensington-Wheaton Policy
area
This
authorization includes
all
necessary planning, design. site improvements, construction.
equipment, and structures.
Approved:
Craig Rice, President, County Council
Date
Approved:
Isiah Leggett, County Executive
Date
This is a correct copy ofCouncil action.
Linda M. Lauer, Clerk of the Council
Date
 PDF to HTML - Convert PDF files to HTML files
Expedited Bill XX - 14
Wheaton Redevelopment Program
Legislative Request Report
1.
Description - The County Executive requests that capital project No. 150401 Wheaton
Redevelopment Program be authorized as a "Special Capital Improvements Project" pursuant
to Section §302 ofthe County Charter and Section §20-1 ofthe Montgomery County Code.
Problem - Section §302 ofthe County Charter and Section §20-1 ofthe County Code require
certain capital improvement projects to be individually authorized by law
if
the locally-funded
cost is projected to exceed $13,621,000 in FY15 dollars. The estimated locally-funded cost of
this project in the Recommended County Executives FYI5 Capital Budget and FY15-20 Capital
Improvements Program is $142,579,000 for planning, design, land, site improvement and
utilities, and construction costs.
Goals and Objectives - This project provides for the for the planning, studies, design, and
construction of an office building, public parking garage, and a
town
square on the site of
Parking Lot
13
and the Mid-County Regional Services Center
(RSC)
in the Kensington­
Wheaton Policy area.
Coordination - This project has been coordinated with WMATA, Office ofthe County Attorney,
M-NCPPC, Westfield Mall, Community Associations and Residents, Private developers,
Department of General Services, Department of Transportation, Department ofEnvironmental
Proection, Department ofPermitting Services, Department of Housing and Community Affairs,
Mid-County Regional Service Center, and State of Maryland.
Fiscal Impact - The total estimated cost for this project is $143,847,000 with $142,579,000 in
< local funding.
Impact - The public investment will create a centrally located public space and a daytime
population that together will contribute to an IS-hour economy in downtown Wheaton.
Evaluation - Capital< projects are evaluated biennially by the County Executive and County
Council as part of the Capital Improvements Program review.
Experience Elsewhere - Not Applicable.
Sources of Information - Al Roshdieh, Department of Transportation..
Applications Within Municipalities - Not Applicable.
Penalties - None Required.
2.
3.
4.
5.
6.
7.
S.
9.
10.
II.
 PDF to HTML - Convert PDF files to HTML files
Fiscal Impact Statement
Council Expedited Bill XX-14, Special Capital Improvements Project
.Wheaton Redevelopment Program
1.
Legislative Summary.
Section §302 of the County Charter and Section §20-1 of the County Code require certain
capital improvement projects to be individually authorized by law
if
the locally-funded
cost is projected to exceed $13,621,000 in FY15 dollars. The Executive requested a bill
for one project Wheaton Redevelopment Program - that now requires Special Capital
Improvement Proj ect legislation.
2. An estimate of changes
in
County revenues and expenditures regardless of whether
the revenues or expenditures are assumed
in
the recommended or approved budget.
Includes source of information, assumptions, and methodologies used.
There are no expenditures or revenues associated with this bill. The bill only authorizes
the designation of the Wheaton Redevelopment Program as a Special Capital
Improvement Project.
3. Revenue and expenditure estimates covering at least the next 6 fIscal years.
See item #2 above .
. 4. An actuarial analysis through the entire amortization period for each bill that would
affect retiree pension or group insurance costs.
Not applicable. There are no personnel costs associated with this bill.
5. Later actions that may affect future revenue and expenditures
if
the bill authorizes
future spending.
Not applicable.
6. An estimate of the staff time needed to implement the bill.
Not applicable. This bill does not affect staff responsibilities.
7. An explanation of how the addition of new staff responsibilities would affect other
duties.
Not applicable.
8. An estimate of costs when an additional appropriation is needed.
Not applicable.
 PDF to HTML - Convert PDF files to HTML files
9. A description of any variable that could affect revenue and cost estimates.
Not applicable.
10. Ranges of revenue or expenditures that are uncertain or difficult to project.
Not applicable.
11.
If
a bill
is
likely to have no fIScal impact, why that
is
the case.
This bill authorizes the designation of the project as a Special Capital Improvement
project. No new appropriation is required.
12. Other fIScal impacts or comments.
None.
13. The following contributed to and concurred with this analysis: (Enter name and
department).
Helen P. Vallone, Office of Management and Budget.