Look Ahead - Week of March 17 to March 23, 2019

Headliner

CONSTRUCTION OF SEVENTH FLOOR UNDERWAY

Project Status

The project remains on-schedule for a May 27, 2020 substantial completion. Building occupation and tenant move-in is scheduled during early-summer 2020.

Garage

Electrical work, block masonry, door frames, and sprinkler installation continues at Levels P3, P2, P1, and P0.

Office Building

First Floor

Concrete Complete

Rough-in of mechanical and piping underway.

Second Floor

Concrete Complete

Rough-in of mechanical and piping underway. A mock-up of a bathroom underway.

Third Floor

Concrete Complete

Fourth Floor

Concrete Complete

Fifth Floor

Concrete Complete

Sixth Floor

Concrete Complete

Seventh Floor

Concrete pours #1 and #2 will take place this week, weather permitting. Construction of the 7th floor will complete next week, weather permitting.

Seventh Floor

Seventh floor under construction

Column Construction

Column construction underway between the 7th and 8th floors.

Utility Construction

Pepco relocations are complete with exception of pole removal that will follow removal of the overhead Verizon lines.

Verizon Underground Work

Complete

WSSC

The contractor will be working in Ennalls this week to abandon the old WSSC line. This work will be pursued during normal work hours using traffic controls and flagman.

Town Plaza

The Town Plaza will include an amphitheater, stage, lighting, art work, Wi-Fi, bio-retention areas, landscaping, and elevated walkways from the new Town Plaza to Georgia Ave (to the south) and to the WMATA tower connecting to the WMATA parking garage located on Veirs Mill Road.

Rough grading is complete. Underground storm drain installation has commenced.

Follow Project Progress via the Project Camera

A camera has been installed to view construction on the site. Click here to access the camera.

Upcoming and Ongoing Activities:

  • Commence concrete placement of 7th floorr
  • Building column construction 7th floor to 8th floor
  • Plumbing and mechanical commenced on the first and second floors
  • A bathroom mock-up is underway on the second floor
  • Placement of concrete block, door frames, piping, sprinklers, and electrical in the garage on Levels P2 and P1 (P3 and P4 complete)
  • Offsite material fabrications underway
    • Stone
    • Misc metals
    • Windows
    • Building skin
    • Chillers HVAC
    • Interior lights
  • Town Plaza (South of Reedie Drive)
    • Demolition of Concrete
    • Excavation and haul-off
    • Rough grading