Skip to main content

Click here to access previous calendar activities for Wheaton project.

Click here for Newsletter Archives (pdf)

Look Ahead – Week of July 7 to July 13, 2019

Headliner

CONSTRUCTION OF THE PENTHOUSE ROOF UNDERWAY

Project Status

Project Status: The project remains on-schedule for a May 30, 2020 substantial completion and is currently 67-percent complete.

Interior work including: mechanical, electrical, duct, sprinkler, plumbing, and interior wall framing is underway through the 8th floor. The exterior sheathing installed through floor 11 (see photo). Window installation through the 9th floor. Storefront glass is installed along Triangle Lane where the new retail businesses will locate.

Building occupation and tenant move-in is scheduled during summer 2020.

Garage

Electrical, mechanical, and sprinkler installation nearly complete.

Painting is underway.

Office Building

First Floor

Concrete complete

Rough-in of mechanical, electrical, and piping underway.

Duct installation ongoing.

Stairs erected.

Interior walls are being framed.

Storefront glass installed along Triangle Lane at the retail spaces.

Glass-front installed at Reedie Drive.

Curtain wall framing installation underway.

Second Floor

Concrete complete

Rough-in of mechanical, electrical, and piping underway.

Duct installation ongoing.

A mock-up of the 2nd floor bathroom is underway.

Stairs erected.

Interior walls framing complete.

Curtain wall framing installation underway.

Third Floor

Concrete complete

Rough-in of mechanical, electrical, and piping underway.

Duct installation underway.

Interior walls framing complete.

Exterior sheathing installation underway.

Waterproofing (blue skin) installation underway

Window installation commenced.

Stairs erected.

Fourth Floor

Concrete complete

Rough-in of mechanical, electrical, and piping underway.

Interior walls are being framed.

Exterior sheathing installation underway.

Waterproofing (blue skin) installation underway

Stairs erected.

Fifth Floor

Concrete complete

Rough-in of mechanical, electrical, and piping underway.

Exterior sheathing installation underway.

Window installation

Waterproofing (blue skin) installation underway

Sixth Floor

Concrete complete

Rough-in of mechanical, electrical, and piping underway.

Exterior sheathing installation underway.

Window installation

Seventh Floor

Concrete complete

Exterior sheathing installation ongoing.

Rough-in of mechanical & electrical

Eighth Floor

Concrete complete

Sheathing installation underway.

Rough-in of mechanical & electrical

Ninth Floor

Concrete complete

Sheathing installation underway.

Tenth Floor

Concrete complete

Eleventh Floor

Concrete complete

Twelfth Floor

Concrete complete

Thirteenth Floor

Forming and reinforcing started.

Fourteenth Floor

The first concrete pour took place Monday, June 3. The second (and final) concrete pour on the 14th floor is scheduled on Wednesday, June 5, weather permitting.

Progress July 9

June 25, 2019

Penthouse

Penthouse floor-slab complete.

Penthouse roof being framed.

Progress July 9

July 8, 2019 - Interior piping and framing - Third floor

Note: Verizon underground work in Triangle lane is complete.

Utility Work

Sanitary sewer work along Veirs Mill Road will continue this week. Sanitary sewer work will continue this week at night between the hours of 9pm and 5am and have little impact on traffic.

Town Plaza

The Town Plaza will include an amphitheater, stage, lighting, art work, Wi-Fi, bio-retention areas, landscaping, and elevated walkways to Georgia Ave (to the south) and to the WMATA tower connecting to the WMATA parking garage located on Veirs Mill Road.

The contractor is forming and placing foundation elements for the stage, bio-retention areas, and the elevated walkways. This work will continue over the next several weeks.

Follow Project Progress via the Project Camera

A camera has been installed to view construction on the site. Click here to access the camera.

Upcoming and Ongoing Activities:

  • Complete elevator machine room
  • Frame and pour Penthouse roof
  • Plumbing, electrical, and mechanical installations continues on floors through 9th floor
  • Interior wall framing on floors 4 through 6
  • Exterior sheathing installation complete through the 9th floor and climbing
  • Application of blue-skin waterproofing complete through the 9th floor and climbing
  • Sanitary sewer work in Veirs Mill Road (night work) will continue this week
  • Offsite material fabrications underway
    • Stone
    • Misc metals
    • Windows
    • Building skin
    • Chillers HVAC
    • Interior lights
  • Town Plaza (South of Reedie Drive)
    • Rough grading complete
    • Installation of storm drain lines underway
    • Drilling of micro-piles
    • Placement of concrete foundations for elevated walkways
    • Placement of concrete foundations for bio-retention areas
    • Placement of concrete foundations for stage
Go Top