Childcare at Woodlin Elementary School

Level of Effort Program: Childcare Renovations

Special Notice: Place Holder for special notice

Notice: Project Completed

Show the project location in google map 2103 Luzerne Avenue, Silver Spring, MD 20910

Childcare at Lawton Community Center

Funding/Expenditure Schedule: APPROVED

Project Team

Montgomery County Government
Department of General Services

Division of Building Design & Construction

Division Chief: Hamid Omidvar, AIA
Hamid.Omidvar@montgomerycountymd.gov
Section Chief: Suresh Patel
Project Manager: Catherine Sheehan

Project Partner

Montgomery County Public Schools

Architect / Engineer

Design Collective, Inc.
Adtek Engineers, Inc.
Rathgeber/Goss Associates
James Posey Associates, Inc.
Playground Specialists, Inc.

Construction Manager

Oak Contracting, LLC

For operations inquiries. Please contact.

Montgomery County Department of Health and Human Services

240-777-0311

Current Phase: Construction

Project Schedule:

Phase 1 - Parking Spaces Repair
Construction commenced on April 23,2018
Construction completed September 2019
Phase 2 - Stair Towers Renovation
Construction commenced on September 23, 2019
Construction will be completed August 2021

Construction began in January 2022 and is expected to be completed in the Winter of 2023/2024.

Live Project Video

Ribbon Cutting Ceremony

Event Images

Event Images

Event Image

This childcare center is on Montgomery County Board of Education property and until demolition in early 2022 was in a freestanding modular structure west of Woodlin Elementary School (ES). The Department of Health and Human Services (DHHS), Child Care in Public Space (CCIPS) Program licenses space to Rockville Day Care Association (RDCA) to provide childcare services for approximately 100 children of families in the Woodlin ES community at this location. The center is staffed by approximately 22 people and operates Monday through Friday from 7:00 AM until 6:30 PM. Parking for the childcare center is shared with the elementary school.

The aging modular structure was deemed to be in poor physical condition during a survey conducted in 2020. Prior to demolition, the childcare center had a dedicated playground for children ages 0-5. School-age children enrolled with RDCA used the elementary school playground before and after school.

Early in 2020, Montgomery County Public Schools (MCPS) began designing a structure that would replace the existing Woodlin ES. It was determined that in lieu of building a separate structure for the childcare center, the best use of the site would be to include it within the same structure as the school. DGS, DHHS, MCPS, and their project team, along with RDCA and neighborhood representatives worked together to develop the design and a strategy for completing the project.

Colocation of the school and childcare maximizes the use of the building and site benefitting both entities. The childcare wing will have the capacity to serve up to 97 children in six (6) classrooms and RDCA will have the opportunity to bid for use of supplemental space within the elementary school to serve additional school-age children before and after school hours. The childcare playground is designed for children ages 0-5 and will be used by pre-kindergarten children who attend Woodlin ES. Playgrounds associated with the school are designed for children ages 5-12 and will be used by school-age children who are enrolled for before and/or after care at the childcare center.

Temporary accommodations for the childcare center, including a dedicated playground, were constructed in late 2021 at Parkside Headquarters on Brunett Avenue in Silver Spring. RDCA began providing services there in January 2022 and expect to move back to the new facility when construction is complete in the winter of 2023/2024.

Architectural and Construction Images

Female Corridor at Nurse Station

Female Corridor at Nurse Station

Female Corridor at Nurse Station

Lobby 200 Looking Nurse 212

Architectural Images

Site Location Map

Site Location Map

Site Location Aerial Map

Site Location Aerial Map

Former Childcare at Woodlin Elementary School – Aerial View

Former Childcare at Woodlin Elementary School – Aerial View

Former Childcare at Woodlin Elementary School - Playground

Former Childcare at Woodlin Elementary School - Playground

4	Site Plan (Childcare wing in blue; childcare playground in green)

4 Site Plan (Childcare wing in blue; childcare playground in green)

Floor Finish Plan and Corridor 3D View

Floor Finish Plan and Corridor 3D View

Floor Finish Materials

Floor Finish Materials

Wall Finish Plan, Elevations and Materials

Wall Finish Plan, Elevations and Materials

Millwork & Wall Protection Plan, Elevations and Materials

Millwork & Wall Protection Plan, Elevations and Materials

Architectural and Construction Images

Building 3D View with Childcare center in foreround

Building 3D View with Childcare Center in foreground

Building 3D View with Childcare center in foreround

Playground 3D View (Image of building in background does not reflect design)

Construction Images

Childcare Renovation at Woodlin Elementary School

Woodlin Elementary School and Childcare Center entry drive with sidewalk and landscaping – view from SW corner. (3/29/24).

Childcare Renovation at Woodlin Elementary School

Playground and sitework continues, ceiling and flooring installed, shelving in place. Classroom – view looking east. (3/29/24).

Childcare Renovation at Woodlin Elementary School

Woodlin Elementary School entry drive and sidewalk with Childcare Center beyond – view from SW corner. (2/22/24).

Childcare Renovation at Woodlin Elementary School

Childcare Center walls painted, flooring installed under protection board, shelving and cubbies ready to place. Classroom – view looking west. (2/22/24).

Childcare Renovation at Woodlin Elementary School

Woodlin Elementary School and Childcare Center entry drive and sidewalk work progressing – view from SW corner. (1/29/24).

Childcare Renovation at Woodlin Elementary School

Childcare Center first coat of paint, doors, ceiling grid, light fixtures and mechanical units installed in many areas. Classroom – view looking west. (1/29/24)(12/28/23)

Childcare Renovation at Woodlin Elementary School

Wall in front of Childcare Center playground in progress – view from SE corner. (12/28/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center drywall and mechanical systems installed in many areas. Classroom – view looking west. (12/28/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center sidewalk and driveway work progressing – view from SW corner. (11/27/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center drywall installed on both sides of studs in many areas. Corridor – view looking north. (11/25/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center window and door frame installation complete; sitework progressing – view from SW corner with entrance canopy on right and school entrance on left. (10/23/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center drywall installed on one side of studs. Corridor – view looking north. (10/23/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center window installation started – view from SW corner with entrance canopy on right and school entrance on left. (10/5/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center door frame and HVAC unit installation progressing. Corridor – view looking north. (9/28/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center brick installation complete – view from SW corner with entrance canopy on right and school entrance on left. (9/5/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center interior partition framing, piping, blocking ductwork & wiring. Corridor – view looking south. (8/29/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center staging for brick installation – view toward SW corner with entrance canopy on right. (7/26/23)

Childcare Renovation at Woodlin Elementary School

Childcare Center interior partition framing, piping and blocking – view looking north. Corridor and preschool classroom entry on left; and kitchen with mechanical room and roof access in background on right. (7/26/23)

Childcare Center exterior sheathing – view toward SW corner with entrance canopy on right. (6/13/23)

Childcare Center exterior sheathing – view toward SW corner with entrance canopy on right. (6/13/23)

Childcare Center interior partition framing and ductwork – view from preschool classroom looking south through the building toward the entrance. Other classrooms and support spaces in background. (6/23/23)

Childcare Center interior partition framing and ductwork – view from preschool classroom looking south through the building toward the entrance. Other classrooms and support spaces in background. (6/23/23)

Childcare Center exterior framing – view toward SE corner with entrance canopy on left. (5/23/23)

Childcare Center exterior framing – view toward SE corner with entrance canopy on left. (5/23/23)

Childcare Center steel structure – view from entrance looking north through the building. Woodlin Elementary School in background. (5/23/23)

Childcare Center steel structure – view from entrance looking north through the building. Woodlin Elementary School in background. (5/23/23)

Childcare Center steel structure – view from future entry drive toward SW corner. (5/2/23)

Childcare Center steel structure – view from future entry drive toward SW corner. (5/2/23)

Childcare Center steel structure – view from SE corner looking north toward Woodlin Elementary School. (5/2/23)

Childcare Center steel structure – view from SE corner looking north toward Woodlin Elementary School. (5/2/23)

Underslab gravel placement for Childcare Center looking north with ES gym wall in background. (2/15/23

Childcare Center steel structure – view from future entry drive toward SW corner. (3/30/23)

Underslab gravel placement for Childcare Center looking west. (2/15/23)

Childcare Center steel structure – view looking east through the building. (3/30/23)

Underslab gravel placement for Childcare Center looking north with ES gym wall in background. (2/15/23

Underslab gravel placement for Childcare Center looking north with ES gym wall in background. (2/15/23)

Underslab gravel placement for Childcare Center looking west. (2/15/23)

Underslab gravel placement for Childcare Center looking west. (2/15/23)

Trench work for underground plumbing and electrical conduits – view from SW (1/24/23)

Trench work for underground plumbing and electrical conduits – view from SW (1/24/23)

Underground sanitary pipes and trenches with school gym walls in background – view from SE (1/24/23)

Underground sanitary pipes and trenches with school gym walls in background – view from SE (1/24/23)

•	Childcare Center foundation wall – view from future parking lot on west side with school gym on left (12/9/22

Childcare Center foundation wall – view from future parking lot on west side with school gym on left (12/9/22)

Childcare Center foundation wall – view from future playground on east side with school gym on right (1/6/23

Childcare Center foundation wall – view from future playground on east side with school gym on right (1/6/23)

Footing in Childcare Center area (11/7/22)

Footing in Childcare Center area (11/7/22)

Foundation wall in Childcare Center area (11/8/22)

Foundation wall in Childcare Center area (11/8/22)

Architectural and Construction Image

TBD