RESIDENTIAL ROADWAY RESURFACING OUTLOOK

Below is the tentative concrete infrastructure schedule for our FY20 construction season, which begins July 1, 2019. Please check back periodically as projects are added or scheduled.

This schedule may be changed and substitutions may be made at any time due to weather and/or operational reasons.

Updated: March 15, 2019

Proposed Concrete Projects

 

Project Location Program Year
Boland Farm Road Summer 2019
Westlake Drive Summer 2019

 