White Oak Middle School Stormwater Practice Upgrades

 

As a part of the County’s effort to protect our waters, White Oak Middle School was selected for a county facilities project to help reduce stormwater pollution that drains into our streams. County Facilities projects generally involve installing small-scale stormwater practices to capture water from rooftops, roadways, and sidewalks during storms. County Facilities projects incorporate many of the same practices as Green Streets projects.

Residents surrounding the White Oak Middle School project area can also help reduce stormwater pollution by installing stormwater practices on their property through the County's Targeted RainScapes Neighborhood program.

Various public events will be held throughout the project phases for staff, students and parents to learn about the project and to provide input on the design of the project. 

 

 

 

Map of White Oak Middle School Project
To download a copy, (PDF 405KB) 

 

Public Events and Site Schedule*

Calendar graphic

Survey and Site Analysis

Completed Summer 2013

Calendar graphic

Preliminary Site Assessment

Completed Fall 2013

Calendar graphic

Public Meeting

If needed
TBD

Calendar graphic

Concept Design Plans

Completed Fall 2014

Calendar graphic

Site Walk

If needed
TBD

Calendar graphic

Final Plans

Fall 2015

Calendar graphic

Construction

Summer 2016