Kensington Volunteer Fire Station 5, Resurfacing
Montgomery County Government
Department of General Services
Division of Building Design & Construction
Division Chief: Hamid Omidvar, AIA[email protected]
Section Chief: Randall Hawkins
Project Manager: Gary Colton
Architect / Engineer
NOA Architects, Planning & Interiors, LLCContractor
D&F ConstructionFor operations inquiries. Please contact.
Current Phase: Construction
The contractor started construction on October 18, 2023, and achieved substantial completion of all resurfacing on February 21, 2024. The contractor completed the minor repairs on June 7,2024 and the punch list work is being addressed.
The scope of work will be to repair and resurface the parking lot and to provide ADA accessible routes of access to the public meeting room and public entrance along with required ADA parking.
Architectural and Construction Images