Project Milestone Schedule
Substantial Completion – November 2022
Permanent Closure of Executive Blvd – Mid May 2020
Grand Park Ave – May 2020 to April 2021
Towne Rd – April 2021 to November 2022
Old Georgetown Rd – May 2020 to November 2022
Storm Drain on Old Georgetown Rd – May 2020 to October 2021
Pepco Conduit Construction – May 2020 to July 2021
Pepco Underground and Overhead Relocation – Summer/Fall 2021
VZ Underground and Overhead Relocation – Ongoing through December 2021
Newsletter Archive
Week of February 7, 2020
Week of January 3, 2020
Week of November 29, 2020
Week of November 1, 2020
Week of October 4, 2020
Week of September 6, 2020
Week of August 9, 2020
Week of July 12, 2020
Week of June 15, 2020
Week of May 17, 2020
Week of April 19, 2020
Week of March 22, 2020
Week of March 8, 2020
Week of February 9, 2020
Week of January 26, 2020
Week of January 12, 2020
Week of December 29, 2019
Week of December 15, 2019
Week of December 1, 2019
Week of November 17, 2019
Week of November 3, 2019
Week of October 20, 2019
Week of September 22, 2019
Week of August 25, 2019
Week of August 11, 2019
Week of July 28, 2019
Week of July 14, 2019
Week of June 30, 2019
Week of June 16, 2019
Week of June 2, 2019
Week of May 19, 2019
Week of May 5, 2019
Week of April 21, 2019
Week of April 7, 2019
Week of March 24, 2019
Week of March 10, 2019
Week of February 24, 2019
Week of February 10, 2019
Week of January 27, 2019
Week of January 13, 2019
Week of January 6, 2019
Go Top